Phase 20.23-20.26 Executive Summary

作成日: 2025-10-30 分析者: Claude (based on User's critical insight)


🔥 Critical Discovery

User の洞察:

"Arc/RefCell はHakoruneスクリプトで実装するやつじゃない"

Impact: 完全に正しい! - これによりロードマップが劇的に改善


📊 Timeline Transformation

Before (C Implementation - Original Plan)

Phase 20.23: Arc/RefCell (C)    2-3 months ❌ High risk
Phase 20.24: Box System         3-4 months
Phase 20.25: Rust削除           2-3 months
────────────────────────────────────────────
Total:                          7-10 months
Risk:                           HIGH ❌
Complexity:                     HIGH ❌

After (Hakorune Implementation - This Plan)

Phase 20.23: Arc/RefCell (Hako) 2-3 weeks ✅ Low risk
Phase 20.24: Parser削除         1-2 months
Phase 20.25: Box System削除     2-3 months
Phase 20.26: Final Rust削除     2-3 months
────────────────────────────────────────────
Total:                          6-9 months ✅
Risk:                           LOW ✅
Complexity:                     LOW → MEDIUM ✅

Time Savings: ~2.5 months (10-11 weeks)

Risk Reduction: HIGH → LOW


🎯 Phase-by-Phase Breakdown

Phase 20.23: Arc/RefCell in Hakorune2-3週間

Purpose: メモリ所有権管理の基盤実装

Implementation:

  • Policy Plane: HakoruneArcBox/RefCellBox- ロジック層
  • Data Plane: C100行- 実メモリ操作

Pattern: GcBox と同じ(既に検証済み)

Deliverables:

  • lang/src/runtime/memory/arc_box.hako~100 lines
  • lang/src/runtime/memory/refcell_box.hako~100 lines
  • lang/src/runtime/memory/arc.c~50 lines
  • lang/src/runtime/memory/refcell.c~50 lines

Success Criteria:

  • retain/release/clone 正常動作
  • borrow/borrow_mut 正常動作
  • valgrind cleanmemory leak なし)
  • 4 threads concurrent access で破損なし

Risk: Low Duration: 2-3 weeks


Phase 20.24: Parser削除1-2ヶ月

Purpose: Rust Parser/AST 削除、Hakorune Parser に完全移行

Deletion Target: -10,500 lines

  • src/parser/: -6,000 lines
  • src/ast/: -4,500 lines

Implementation:

  • Month 1: Gate infrastructure + Full smoke testing
  • Month 2: Default flip + File deletion + Documentation

Success Criteria:

  • Rust Parser 完全削除
  • 296/296 smoke tests PASS
  • Hakorune Parser がデフォルト

Risk: Low 完全重複、well-tested Duration: 1-2 months


Phase 20.25: Box System + MIR Builder削除2-3ヶ月

Purpose: Rust MIR Builder/Optimizer/VM/Box System 削除

Deletion Target: -22,193 lines

  • src/mir/builder.rs: -900 lines
  • src/mir/optimizer/: -2,500 lines
  • src/mir/printer.rs: -400 lines
  • src/backend/mir_interpreter/: -2,393 lines
  • src/boxes/: -16,000 lines

Implementation:

  • Month 1: MIR Builder/Optimizer deletionP0 blocker 修正含む)
  • Month 2: Rust VM deletionBridge-B 最適化)
  • Month 3: Box System deletionArc/RefCell 統合)

P0 Blockers:

  • Bridge-B timeout 修正60s → 300s
  • map_len バグ修正0 → 2 返却)

Success Criteria:

  • P0 Blockers 完全解決
  • Hakorune MIR Builder/VM/Boxes がデフォルト
  • 296/296 smoke tests PASS
  • Performance parity±20% 許容)

Risk: Medium ⚠️P0 blocker 依存) Duration: 2-3 months


Phase 20.26: Final Rust Consolidation2-3ヶ月

Purpose: Rust 層最終整理 + hakmem 統合

Deletion Target: -61,713 lines

  • Experimental backendsLLVM/WASM: -6,751 lines
  • Plugin System: -10,000 lines
  • Kernel: -8,000 lines
  • Other cleanup: -36,962 lines

Final State:

  • Rust layer: ~5,000 lines8.3%
  • Hakorune layer: ~55,000 lines91.7%
  • hakmem (C): ~6,500 lines

Implementation:

  • Month 1: Rust layer audit + Wave 1 deletionLLVM/WASM
  • Month 2: Plugin System + Kernel migration
  • Month 3: hakmem integration + Final cleanup

Success Criteria:

  • Rust layer ≤5,000 lines
  • hakmem デフォルトアロケータ
  • True Self-Hosting 達成
  • 296/296 smoke tests PASS

Risk: Medium ⚠️hakmem 統合リスク) Duration: 2-3 months


📈 Cumulative Progress

Phase Duration Lines Deleted Cumulative % Reduction
20.23 2-3 weeks -0 -0 0%
20.24 1-2 months -10,500 -10,500 -9.0%
20.25 2-3 months -22,193 -32,693 -28.0%
20.26 2-3 months -61,713 -94,406 -80.8%
Total 6-9 months -94,406 -94,406 -80.8%

Before → After

Before (Phase 20.23 start):
  Total:        116,841 lines
  Rust (src/):   99,406 lines (85.1%)
  Hakorune:      17,435 lines (14.9%)

After (Phase 20.26 complete):
  Total:         ~66,500 lines
  Rust (src/):    ~5,000 lines (8.3%) ✅
  Hakorune:      ~55,000 lines (91.7%) ✅
  hakmem (C):     ~6,500 lines

Rust reduction: -94,406 lines (-95.0%) 🔥
Ratio flip: 85% Rust → 8% Rust ⚡

Rationale: Foundation → Value → Major Work → Cleanup

Advantages:

  1. Natural dependency flow: Arc/RefCell → Box System
  2. Low risk start: 2-3週間で基盤確立
  3. Consistent momentum: Small win → Big win → Huge win
  4. Early testing: Box System 時に Arc/RefCell は運用実績あり
  5. Simple rollback: 各 Phase ごとに checkpoint

Timeline:

Week 1-3:     Phase 20.23 (Arc/RefCell)      [██░░] Low risk
Month 2-3:    Phase 20.24 (Parser削除)       [████] Low risk
Month 4-6:    Phase 20.25 (Box System削除)   [████] Medium risk
Month 7-9:    Phase 20.26 (Final Rust削除)   [████] Medium risk

Total: 6-9 months
Risk progression: Low → Low → Medium → Medium ✅

Alternative: Option B (Parser First, Arc/RefCell Second)

Why NOT recommended:

  • ⚠️ Momentum gap: Parser 削除後に 2-3週間待ちArc/RefCell 実装)
  • ⚠️ Unnatural flow: Parser は Box System と無関係
  • ⚠️ Testing risk: Box System 時に Arc/RefCell が若い(運用実績少ない)

Verdict: Option A の方が自然で安全


🔧 Technical Architecture

Policy-Data Plane SeparationKey Pattern

Existing Success: lang/src/runtime/gc/gc_box.hako

┌─────────────────────────────────────────┐
│ Policy Plane (Hakorune)                 │
│ - Logic, thresholds, scheduling         │
│ - ArcBox, RefCellBox, GcBox             │
│ - Easy to modify, test, maintain        │
└────────────────┬────────────────────────┘
                 │ call("env.*")
                 ▼
┌─────────────────────────────────────────┐
│ Data Plane (C/Rust)                     │
│ - Actual memory operations              │
│ - Atomic operations, syscalls           │
│ - Hard to modify, but minimal           │
└─────────────────────────────────────────┘

This pattern applies to:

  • GcBox: Policy(Hakorune) + Data(Rust) - already working
  • ArcBox: Policy(Hakorune) + Data(C) - Phase 20.23
  • RefCellBox: Policy(Hakorune) + Data(C) - Phase 20.23
  • Box System: Policy(Hakorune) + Data(C-ABI) - Phase 20.25

Why This Works:

  • Hakorune: 10x faster developmentscript level
  • C: Necessary evilonly for data operations
  • Separation: Clear boundary, easy to test/rollback

🚨 Critical Risks & Mitigation

Phase 20.23 RisksLow

Risk Probability Impact Mitigation
Atomic ops bug Low High C11 standard, existing implementations
Memory leak Medium High valgrind continuous testing
Race condition Low High TSan (Thread Sanitizer)

Overall Risk: Low

Phase 20.24 RisksLow

Risk Probability Impact Mitigation
Hakorune parser bug Low High Already tested (296 tests)
Import cleanup miss Medium Low Cargo build check + CI
Performance regression Low Medium Benchmark + rollback

Overall Risk: Low

Phase 20.25 RisksMedium

Risk Probability Impact Mitigation
P0 Blocker unresolved Medium Critical Week 1-2 専任対応
Performance gap Medium High Subprocess reuse, bytecode cache
Box System parity Low High 1:1 mapping verification

Overall Risk: Medium ⚠️P0 blocker 最優先)

Phase 20.26 RisksMedium

Risk Probability Impact Mitigation
hakmem stability Medium High Extensive testing, fallback to libc
Dependency hell Medium Medium Wave-based deletion
Integration issues Low Medium Monthly checkpoints

Overall Risk: Medium ⚠️hakmem 統合最優先)


💡 Key Success Factors

1. User の Critical Insight

Discovery: "Arc/RefCell はHakoruneスクリプトで実装するやつじゃない"

Impact:

  • 2.5ヶ月の時間短縮
  • リスク大幅削減C実装 → Hakorune実装
  • 保守性向上C コード → Hakorune コード)

Lesson: Policy は Hakorune で、Data は C で

2. GcBox Pattern Precedent

Existing: lang/src/runtime/gc/gc_box.hako(既に動作確認済み)

Pattern: Policy(Hakorune) + Data(Rust/C) separation

Application: Arc/RefCell, Box System に適用可能

3. Incremental Approach

Strategy: 4 phases, monthly checkpoints, granular gates

Rollback: 各 Phase ごとに Git tag + backup branch

Validation: 毎 Phase で 296/296 smoke tests PASS

4. Data-Driven Decisions

Benchmark: 継続的に performance 測定

Metrics: Lines deleted, risk level, test coverage

Adjustment: データに基づいて計画調整


🎉 Expected Final Outcome

Quantitative Results

Starting State (Phase 20.23 開始時):
├─ Total codebase:     116,841 lines
├─ Rust layer:          99,406 lines (85.1%)
└─ Hakorune layer:      17,435 lines (14.9%)

Final State (Phase 20.26 完了時):
├─ Total codebase:      ~66,500 lines
├─ Rust layer:           ~5,000 lines (8.3%) ✅
├─ Hakorune layer:      ~55,000 lines (91.7%) ✅
└─ hakmem (C):           ~6,500 lines

Reduction: -94,406 lines (-80.8%)
Ratio flip: 85% Rust → 8% Rust ⚡

Qualitative Results

True Self-Hosting Achieved:

  • Rust = Floor~5,000 lines - minimal foundation
  • Hakorune = House~55,000 lines - everything
  • hakmem = Plumbing~6,500 lines C - memory

Clean Architecture:

  • Policy-Data plane 完全分離
  • Hakorune で logic、C で data operations

Memory Safety:

  • hakmem allocatorcall-site profiling
  • Arc/RefCellatomic reference counting
  • valgrind clean

Performance Parity:

  • ±10-20% vs original Rust implementation
  • Acceptable tradeoff for self-hosting

Maintainability:

  • Hakorune code is readablevs C/Rust
  • Easy to test at script level
  • Clear boundaries and interfaces

📚 Documentation Deliverables

Phase-by-Phase READMEs

  1. Phase 20.23: Arc/RefCell in Hakorune

    • Hakorune implementation strategy
    • Week-by-week plan
    • C data plane API100 lines
  2. Phase 20.24: Parser削除

    • Gate infrastructure
    • Smoke test validation
    • -10,500 lines deletion
  3. Phase 20.25: Box System + MIR Builder削除

    • P0 blocker resolution
    • Bridge-B optimization
    • -22,193 lines deletion
  4. Phase 20.26: Final Rust Consolidation

    • hakmem integration
    • Final cleanup
    • -61,713 lines deletion

Analysis Documents

  1. Phase Order Analysis: PHASE_ORDER_ANALYSIS.md

    • Option A vs B vs C comparison
    • Risk matrix
    • Timeline visualization
  2. Executive Summary: EXECUTIVE_SUMMARY.md ← This document

    • High-level overview
    • Key decisions
    • Expected outcomes

Reference Materials


🚀 Next Steps

Immediate ActionsWeek 1

  1. Review this plan with stakeholders
  2. Approve Phase 20.23 commencement
  3. Set up tracking (milestones, issues)
  4. Start Arc/RefCell C data plane implementation

Month 1 Goals

  • Phase 20.23 completeArc/RefCell
  • Phase 20.24 startedParser gate infrastructure
  • Weekly check-ins to monitor progress

Month 2-3 Goals

  • Phase 20.24 completeParser削除
  • -10,500 lines reduction achieved
  • Checkpoint: Early value delivered

Month 4-9 Goals

  • Phase 20.25 completeBox System削除
  • Phase 20.26 completeFinal Rust削除
  • True Self-Hosting Achieved

📞 Contact & Questions

Plan Author: Claudebased on User's critical insight Date: 2025-10-30 Review Required: Yesstakeholder approval Start Date: TBDafter approval

Questions:

  • Clarifications needed? → Check detailed Phase READMEs
  • Alternative proposals? → See PHASE_ORDER_ANALYSIS.md
  • Risk concerns? → Each Phase has Risk Analysis section

Approval Checklist

  • Executive summary reviewedthis document
  • Phase 20.23-20.26 READMEs reviewed
  • Phase order analysis reviewed
  • Risk mitigation strategies accepted
  • Resource allocation confirmed1 team, 6-9 months
  • Rollback plan understoodGit tags, backup branches
  • Success criteria agreed-94,406 lines, 296/296 tests PASS
  • Go/No-Go decision: [ ] GO [ ] NO-GO

Summary: User の洞察により、2.5ヶ月短縮リスク大幅削減を達成。Hakorune実装パターンGcBox precedentを Arc/RefCell に適用し、6-9ヶ月で 95% Rust 削減を実現する計画が完成。

Recommendation: Approve and commence Phase 20.23